Evergy was mandated to conduct Technical Due Diligence for a Battery Energy Storage System (BESS) project under development in Apeldoorn, The Netherlands.

The BESS was planned to be installed at the border of the city of Apeldoorn, on the site of an existing solar PV plant that has been operational for two years. To accommodate the BESS, a small section of the PV installation is to be dismantled. At the time of the mandate, both the building permit and grid connection agreement were already in place. The BESS was expected to connect at the same medium-voltage interconnection point used by the existing PV plant.

The services of Evergy comprised in particular:

  • Verification of the technical concept
  • Review of technical design
  • Assessment of permitting status
  • Review of existing grid connection contract and required amendment for the BESS

Country

Netherlands

Year of Mandate

2023

Key Technical Data

  • 15 MW / 30 MWh BESS

Services

Technical Due Diligence

Evergy Engineering GmbH » Appeldorn
Joshua Schwall backpacker, working @evergy since 2015
Ich bin direkt nach dem Studium zu Evergy gegangen. Dabei wurde ich sehr gut betreut und gefördert. Hier habe ich das Gefühl etwas Sinnvolles zu tun. Ich erinnere mich noch an eine Inspektionsreise nach Portugal: In der Mitte des Projektareals war ein Wasserlauf, den wir nur mit dem Geländewagen überqueren konnten und ein kleines, verlassenes Dorf, das erhalten wurde. Das war schon ungewöhnlich.
I joined Evergy straight after my studies. I received very good support and encouragement. I have the feeling that I am doing something meaningful here. I still remember an inspection trip to Portugal: in the middle of the project area was a creek that we could only cross by off-road vehicle and a small, deserted village which was preserved. That was quite unusual.
meet Joshua
Explore more Energy Storage projects