Evergy was commissioned to perform a Confirmatory Technical Due Diligence of five operational hydroelectric power plant schemes across Norway.

The run-of-river plants are geographically distributed between Oslo in the south and Tromsø in the north. Commissioned between November 2011 and December 2015, the plants range in nominal capacity from 1.3 MW to 5.5 MW each. All installations are connected at the medium-voltage level to the respective local distribution networks.

The services of Evergy comprised in particular:

  • Verification of the specific catchment area and hydrological flow assessments
  • Energy yield assessment based on operational data
  • Identification of technical issues affecting operational performance
  • Structural integrity verification of the power plant infrastructure
  • On-site inspection and evaluation of current technical condition
  • Preparation of a refurbishment strategy with estimated cost implications

Country

Norway

Year of Mandate

2022

Key Technical Data

  • Portfolio of 5 run-of-river hydroelectric plants with approx. 16 MW total installed capacity

Services

Energy Forecasts

Technical Due Diligence

Technical Inspection

Evergy Engineering GmbH » Tikraft
Federico Ceriani musicophile, working @evergy since 2008
Da un impianto solare in Italia ad una centrale idroelettrica in Scozia: le sfide possono contribuire ad interessanti risultati e generare nuove idee. Sono aperto per ogni tipo di nuovo progetto.
From a solar park in Italy to a hydro power plant in Scotland: challenges can lead to interesting outcomes and generate new ideas. I’m open-minded for any new type of project.
meet Federico