Evergy was mandated to conduct Technical Due Diligence for a Battery Energy Storage System (BESS) project under development in Apeldoorn, The Netherlands.

The BESS was planned to be installed at the border of the city of Apeldoorn, on the site of an existing solar PV plant that has been operational for two years. To accommodate the BESS, a small section of the PV installation is to be dismantled. At the time of the mandate, both the building permit and grid connection agreement were already in place. The BESS was expected to connect at the same medium-voltage interconnection point used by the existing PV plant.

The services of Evergy comprised in particular:

  • Verification of the technical concept
  • Review of technical design
  • Assessment of permitting status
  • Review of existing grid connection contract and required amendment for the BESS

Country

Netherlands

Year of Mandate

2023

Key Technical Data

  • 15 MW / 30 MWh BESS

Services

Technical Due Diligence

Evergy Engineering GmbH » Appeldorn
Marc Böhnke sailor, working @evergy since 2007
Die Erwartungen unserer Kunden sind hoch, die müssen und wollen wir auch erfüllen. Das geht nur durch persönliches Engagement und Fokus auf die Kundenbedürfnisse.
Our clients’ expectations are high and we have to, and want to, fulfill them. This can only be achieved through personal commitment and a focus on our clients’ needs.
meet Marc
Explore more Energy Storage projects