Hybrid Project
Scruf Dyke

Evergy provided comprehensive lender’s technical due diligence services for the Scurf Dyke Hybrid Power Plant in the UK. The scope included a detailed review of construction timelines, technology selection, permitting, grid connection arrangements, financial model assumptions, ESG compliance, and all key project contracts.

The Scurf Dyke project comprises an 80 MWp solar PV plant integrated with an 8 MW / 16 MWh battery energy storage system (BESS)—the largest of its kind in the UK at the time of engagement. The project was in the development stage and required close coordination among the developer, equity investor, and debt provider.

The services of Evergy comprised in particular:

  • Lender's Technical Due Diligence
  • Construction monitoring with regular site inspections and detailed risk analysis
  • Technical inspections at key milestones (Provisional and Final Acceptance - PAC and FAC)

Country

United Kingdom

Year of Mandate

2024

Key Technical Data

  • 80 MWp PV Plant, 8 MW / 16 MWh BESS

Services

Energy Forecasts

Technical Due Diligence

Technical Inspection

Evergy Engineering GmbH » Scurf Dyke
Joshua Schwall backpacker, working @evergy since 2015
Ich bin direkt nach dem Studium zu Evergy gegangen. Dabei wurde ich sehr gut betreut und gefördert. Hier habe ich das Gefühl etwas Sinnvolles zu tun. Ich erinnere mich noch an eine Inspektionsreise nach Portugal: In der Mitte des Projektareals war ein Wasserlauf, den wir nur mit dem Geländewagen überqueren konnten und ein kleines, verlassenes Dorf, das erhalten wurde. Das war schon ungewöhnlich.
I joined Evergy straight after my studies. I received very good support and encouragement. I have the feeling that I am doing something meaningful here. I still remember an inspection trip to Portugal: in the middle of the project area was a creek that we could only cross by off-road vehicle and a small, deserted village which was preserved. That was quite unusual.