PV Plant
Bartow

Evergy provided Technical Due Diligence services for the acquisition of the Bartow PV Plant and continued to support the Client as Owner’s Engineer throughout the procurement and construction phases.

The Bartow project comprises two PV subsystems with capacities of 200 MWp and 60 MWp, respectively. Both systems are connected to the 380 kV transmission grid through a dedicated medium-voltage cable route and a project-owned 30/380 kV transformer station. Construction of the PV plant commenced in Q1 2024, with commercial operation (COD) planned in Q3 2025.

The services of Evergy comprised in particular:

  • Technical assistance in EPC tender evaluation
  • Support during EPC and O&M contract negotiations
  • Review and approval of detailed EPC engineering design
  • Construction monitoring during project execution
  • Technical inspections at key milestones (PAC and FAC)

Country

Germany

Year of Mandate

2022

Key Technical Data

  • Freefield PV plant with an installed capacity of approx. 260 MWp

Services

Energy Forecasts

Project Planning

Technical Due Diligence

Technical Inspection

Evergy Engineering GmbH » Bartow
Tejas Kuber science buff, working @evergy since 2015
इंग्लंडमध्ये “पेनिके” हा एक चांगला प्रकल्प होता. तो आकारात फार मोठा न्हवता, परंतु मी सुरुवातीपासून प्रकल्पाचा प्रत्येक टप्प्यात साहबगही होतो, साइटवर देखील. मला संपूर्ण प्रक्रियेचे एक चांगले विहंगावलोकन मिळाले.
“Penycae” in England was a great project. It wasn’t huge in size, but I was involved from the start and actively supported it at every project stage, including on-site. I ended up getting a great overview of the entire process.
meet Tejas